Construction Progress Report
Weekly Summary & AI Analysis
Report #RF-2026-007
Date: February 15, 2026
Calendar Week: CW 07
Meteorological Data
Temp. (Min/Max)
2°C / 14°C
Precipitation
0.0 mm
Wind Speed
12 km/h W
Incidents
None
Visual Documentation (3D Scan)

The automated scan comparison shows no significant deviations from the BIM execution model. All MEP penetrations are within the tolerance limit of +/- 10mm.
Personnel Status & Trades
| Trade / Company | Workers |
|---|---|
| Müller Trockenbau GmbH | 4 |
| Schmidt Elektro-Technik | 3 |
| HLS Meisterbetrieb Krauss | 5 |
Capacity Overview
The personnel strength corresponds to 92% of the target value for CW 07. No bottlenecks identified for critical paths.
Progress Status & Defects
Report #RF-2026-007
Trade Progress Report
Studwork 2nd floor installed
Ready for inspection
Cable pulling riser shafts
In progress
Insulation of raw water pipe
Almost done
Substrate preparation bathroom
Starting
Occupational Safety & PPE
PPE check carried out. All participants properly equipped.
Site securing (fences/barriers) without complaint.
Upcoming Milestones
KW 08 - TUESDAY
Delivery of sanitary objects
KW 09 - MONDAY
Beginning of wallpapering
AI Defect Log

Damage to window profile
Drywalling / Zimmer 204
Deep notch on the aluminum profile top left. Risk of corrosion if exposed to weather.

Penetration sealing missing
MEP / Bad 102
Fire collar on riser pipe missing before installation. Violation of fire protection concept.
Overall Assessment
The construction site is in a controlled state. AI-supported error detection enabled proactive corrections before installation. No scheduling risks known.
Inspection report validated